Pillar OMA Logo Home
      

Unusable Data Leaves Asset Maintenance Blocked

Inventory Mapping and Drainage Assessment

PILLAR Pipe Assessment

Problem

After parting ways with their existing maintenance service provider, VDOT Staunton District discovered the data collected by this provider was not transferable to the VDOT system. This left them without the essential data required to maintain its roadway assets within the district.

Solution

PILLAR jumped in to provide the data required to enable VDOT to get a handle on its asset locations, conditions and
maintenance needs. Using mobile LiDAR and our expertise, we collected and assessed the assets quickly and in a manner
consistent with the State’s Maintenance Rating Program (MRP) and InfraTrak.

Approach

PILLAR used a mobile LiDAR scanner to obtain a 3D map of the desired corridor which included point cloud and imagery of the roadside features. Spherical images were captured every 10 feet of traveled pathway.

After post-processing, we identified and labeled asset features and imported them into GIS software.

The client also required drainage pipe assessment so we combined the collected images and point clouds with drainage expertise to perform a boots-on-the-ground condition assessment of 1,080 pipes that met or exceeded the VDOT MRP rating requirements of all drainage structures.

RouteFromToCenterline Miles
I-81Augusta/Rockingham County Line M.P. 237.51West Virginia State Line M.P. 324173
I-66Interchange of I-81 M.P. 300Exit 13 M.P. 1326
I-66Exit 13 M.P. 13M.P. 36.547

Let's Talk

Complete the form below to start a conversation with PILLAR.